SCHEDULE OF FIXED RATES
Labour, Plant & Materials Schedule of Rates
(All Quants re-measurable in accordance with SMM7)
Site Preparation
Site Strip Grass / Rough £0.90/m2
Topsoil scrape (200mm) £2/m2
Reduce Level £4.95/m3
Extra Digging Through Concrete/Brickwork/Rock £29/m3
Breaking out Flags, Tarmac £5/m2
Load Waggons for Muck Away £4.50/t
Large Scale Fill with Exc. Material £4/t
6F2 Filling £19/t
MOT1 Filling £29/t
Disposal on site (<50m) £4/m3
Muck Away £12.50/t
Foundations
Dig Foundation Trenches £14/m3
Concrete to Foundations £130/m3
Ground Floors
Filling with Exc. Materials £5/m3
Underfloor Drains and Water Service Ducts £35/m
Rest Bends and Vertical Pipes £45/ea
Pot and Beam Floors £44/m2
Insulation Jabilite 150 £17/m2
Concrete Screed - Trowelled £20/m2
Plot Drainage & Service Ducts
Trenches (Av 500mm) £8/m
Pipe Bedding £10/m
100mm Plastic Pipework £19.50/m
Extra for Bends / Junctions £38/ea.
Extra for Gullies £60/ea.
Extra for 225 Inspection Chambers £145/ea.
Extra for 450 Inspection Chambers £475/ea.
Service Ducts £16
Scaffolding Mat
Fill with Excavated Materials £4/m3
Fill with Hardcore 6F2 £19/t
Roller/Whacker 6F2 £6.95/m2
External Works (After Scaffold Down)
Clear Site £3/m2
MOT Filling £30/t
Whacker / roll stone £4.95/m2
PCC Flagging £29/m2
Edgings £12/m
Brick Paved Drives £38.25/m2
Clean Sand Fill £20/t
Topsoil Fill £10/t
Turf £2.75/m2
Fence Posts 1.8m £19/ea.
Road Works & Car Parks
6f2 Fill £20/t
MOT1 Fill and Roller 250mm thick) £37/m2
Kerb Race £34/m
Kerbs - All £29/m
Concrete Manholes - 1200 diameter - Av. 1.2m deep £3,250/ea.
Concrete Manholes - 1200 diameter - av. 1.8m deep £5,150/ea.
Hydro-brake £2,150/ea.
150mm clay pipes £61/m
225 Clay Pipes £84/m
Road Gullies £370/ea.
Attenuation £320/m3
Site Mobilisation & Prelims
Site Mobilisation £7,500/Visit
Working Foreman £29.50/h
12T Machine with Driver and Fuel £48.50/h
Schedules of Rates do not apply on small jobs or jobs that have been started by others.