SCHEDULE OF FIXED RATES

Labour, Plant & Materials Schedule of Rates

(All Quants re-measurable in accordance with SMM7)


Site Preparation

  • Site Strip Grass / Rough £0.90/m2

  • Topsoil scrape (200mm) £2/m2

  • Reduce Level £4.95/m3

  • Extra Digging Through Concrete/Brickwork/Rock £29/m3

  • Breaking out Flags, Tarmac £5/m2

  • Load Waggons for Muck Away £4.50/t

  • Large Scale Fill with Exc. Material £4/t

  • 6F2 Filling £19/t

  • MOT1 Filling £29/t

  • Disposal on site (<50m) £4/m3

  • Muck Away £12.50/t

Foundations

  • Dig Foundation Trenches £14/m3

  • Concrete to Foundations £130/m3

Ground Floors

  • Filling with Exc. Materials £5/m3

  • Underfloor Drains and Water Service Ducts £35/m 

  • Rest Bends and Vertical Pipes £45/ea

  • Pot and Beam Floors £44/m2

  • Insulation Jabilite 150 £17/m2

  • Concrete Screed - Trowelled £20/m2

Plot Drainage & Service Ducts

  • Trenches (Av 500mm) £8/m

  • Pipe Bedding £10/m

  • 100mm Plastic Pipework £19.50/m

  • Extra for Bends / Junctions £38/ea.

  • Extra for Gullies £60/ea.

  • Extra for 225 Inspection Chambers £145/ea.

  • Extra for 450 Inspection Chambers £475/ea.

  • Service Ducts £16

Scaffolding Mat

  • Fill with Excavated Materials £4/m3

  • Fill with Hardcore 6F2 £19/t

  • Roller/Whacker 6F2 £6.95/m2

External Works (After Scaffold Down)

  • Clear Site £3/m2

  • MOT Filling £30/t

  • Whacker / roll stone £4.95/m2

  • PCC Flagging £29/m2

  • Edgings £12/m

  • Brick Paved Drives £38.25/m2

  • Clean Sand Fill £20/t

  • Topsoil Fill £10/t

  • Turf £2.75/m2

  • Fence Posts 1.8m £19/ea.

Road Works & Car Parks

  • 6f2 Fill £20/t

  • MOT1 Fill and Roller 250mm thick) £37/m2

  • Kerb Race £34/m

  • Kerbs - All £29/m

  • Concrete Manholes - 1200 diameter - Av. 1.2m deep £3,250/ea.

  • Concrete Manholes - 1200 diameter - av. 1.8m deep £5,150/ea.

  • Hydro-brake £2,150/ea.

  • 150mm clay pipes £61/m

  • 225 Clay Pipes £84/m

  • Road Gullies £370/ea.

  • Attenuation £320/m3

Site Mobilisation & Prelims

  • Site Mobilisation £7,500/Visit

  • Working Foreman £29.50/h

  • 12T Machine with Driver and Fuel £48.50/h

Schedules of Rates do not apply on small jobs or jobs that have been started by others.

 